Analisa Harga Satuan Biaya Alat Berat Berbasis Produktivitas Harian Proyek (Studi Kasus Proyek Pembangunan Stadion Porprov Kota Dumai Tahap I Tahun 2024)

Ilman, Zikri (2025) Analisa Harga Satuan Biaya Alat Berat Berbasis Produktivitas Harian Proyek (Studi Kasus Proyek Pembangunan Stadion Porprov Kota Dumai Tahap I Tahun 2024). Diploma thesis, Politeknik Negeri Bengkalis.

[thumbnail of Abstract] Text (Abstract)
TA-4103221442-ABSTRACT.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.

Download (181kB)
[thumbnail of Bab I Pendahuluan] Text (Bab I Pendahuluan)
TA-4103221442-BAB I PENDAHULUAN.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.

Download (221kB)
[thumbnail of Daftar Pustaka] Text (Daftar Pustaka)
TA-4103221442-DAFTAR PUSTAKA.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.

Download (196kB)
[thumbnail of Full Text] Text (Full Text)
TA-4103221442-FULL TEXT.pdf - Submitted Version
Restricted to Registered users only
Available under License Creative Commons Attribution Share Alike.

Download (5MB) | Request a copy

Abstract

this research analyzes the unit cost of heavy equipment based on daily productivity in the construction project of porprov stadium in dumai city phase i, 2024. the heavy equipment studied includes excavator pc 210, vibro roller, wheel loader, and dump truck. the research method uses a quantitative approach with primary data collection (observation, interviews) and secondary data (project documents, equipment specifications). the results show the highest daily productivity was achieved by the excavator
(2,062.48 m³/day), followed by vibro roller (626.48 m³/day), dump truck (119.6 m³/day), and wheel loader (68.32 m³/day). the daily operational costs for each equipment were rp6,046,142.4 (excavator), Rp.13,087,713.04 (dump truck), rp5,815,610 (vibro roller), and Rp. 4,069,277.52 (wheel loader). the total costs for site clearing and excavation reached Rp. 25,607,804.83, for spreading and compaction
Rp. 3,117,532,795.59, and for gravel backfilling Rp. 45,769,015.78. this study emphasizes the importance of optimizing heavy equipment productivity and costs in large-scale construction projects. the findings can serve as a reference for contractors in budget planning and equipment management, as well as improve the efficiency of similar projects in the future.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Alat berat, produktivitas, biaya operasional, proyek konstruksi, Stadion Porprov
Subjects: 600 – ILMU TEKNIK DAN ILMU TERAPAN > 624 – Teknik Sipil dan Konstruksi > 624.1 – Perencanaan dan Desain Bangunan
600 – ILMU TEKNIK DAN ILMU TERAPAN > 624 – Teknik Sipil dan Konstruksi > 624.2 – Struktur Bangunan dan Material
600 – ILMU TEKNIK DAN ILMU TERAPAN > 624 – Teknik Sipil dan Konstruksi > 624.9 – Perawatan dan Pemeliharaan Bangunan
600 – ILMU TEKNIK DAN ILMU TERAPAN > 624 – Teknik Sipil dan Konstruksi > 624.7 – Teknik Hidrolik dan Pengelolaan Air
600 – ILMU TEKNIK DAN ILMU TERAPAN > 624 – Teknik Sipil dan Konstruksi > 624.6 – Teknik Geoteknik dan Fondasi
Divisions: Jurusan Teknik Sipil > Diploma Tiga (D-III) Teknik Sipil > TUGAS AKHIR
Depositing User: D-III Teknik Sipil A 2022
Date Deposited: 20 Aug 2025 14:17
Last Modified: 21 Aug 2025 04:34
URI: https://eprints.polbeng.ac.id/id/eprint/2047

Actions (login required)

View Item
View Item