Saini, Muhammad Syawal (2025) Analisis Pengaruh Temperatur Casing Turbin dalam Proses Start Up di TG-25 PG-3 PT. Indah Kiat Pulp & Paper Perawang. Other thesis, Politeknik Negeri Bengkalis.
![[thumbnail of Abstract]](https://eprints.polbeng.ac.id/style/images/fileicons/text.png)
1. TA-3204211425-Abstract.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.
Download (68kB)
![[thumbnail of Bab I Pendahuluan]](https://eprints.polbeng.ac.id/style/images/fileicons/text.png)
2. TA-3204211425-Bab I Pendahuluan.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.
Download (252kB)
![[thumbnail of Daftar Pustaka]](https://eprints.polbeng.ac.id/style/images/fileicons/text.png)
3. TA-3204211425-Daftar Pustaka.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.
Download (70kB)
![[thumbnail of Full Text]](https://eprints.polbeng.ac.id/style/images/fileicons/text.png)
4. TA-3204211425-Full Text.pdf - Submitted Version
Restricted to Registered users only
Available under License Creative Commons Attribution Share Alike.
Download (3MB)
Abstract
Steam turbines are critical components in steam power plants that require proper start-up procedures to ensure operational reliability and safety. This study analyzes the effect of turbine casing temperature on the start-up process of Turbine Generator 25 (TG-25) at PG-3 PT. Indah Kiat Pulp & Paper Perawang. The focus of the study is on the differences in startup time based on casing temperature conditions, namely cold startup (<150°C), warm (150–300°C), hot (300–400°C), and extra hot (>400°C). The methods used include direct observation, interviews with operators, and analysis of historical turbine operation data. The research results indicate that turbine casing temperature significantly affects startup duration. Cold startup requires the longest time (7 hours) because it necessitates gradual heating to avoid thermal stress on turbine components. Meanwhile, extra-hot startup has the shortest time (3.33 hours) because the turbine casing is already close to operational temperature. Additionally, the temperature difference between the upper and lower casings must be maintained at ≤50°C to minimize vibration and mechanical damage. In conclusion, the higher the casing temperature, the more efficient the turbine startup process. This study suggests implementing startup procedures based on casing temperature conditions to optimize operational time and extend turbine lifespan.
Item Type: | Thesis (Other) |
---|---|
Uncontrolled Keywords: | Steam turbine, startup, casing temperature, vibration |
Subjects: | 600 – ILMU TEKNIK DAN ILMU TERAPAN > 625 – Teknik Kelistrikan dan Elektronik > 625.2 – Sistem Tenaga Listrik dan Distribusi 600 – ILMU TEKNIK DAN ILMU TERAPAN > 625 – Teknik Kelistrikan dan Elektronik > 625.6 – Instrumentasi dan Pengukuran Listrik 600 – ILMU TEKNIK DAN ILMU TERAPAN > 625 – Teknik Kelistrikan dan Elektronik > 625.3 – Elektronika Daya dan Kontrol |
Divisions: | Jurusan Teknik Elektro > Sarjana Terapan (D-IV) Teknik Listrik > SKRIPSI |
Depositing User: | D-IV Teknik Listrik Kelas B |
Date Deposited: | 27 Aug 2025 03:43 |